Fault tree analysis (FTA) is a failure analysis in which an undesired state of a system is analyzed using boolean logic to combine a series of lower-level events. This analysis method is mainly used in the field of safety engineering to quantitatively determine the probability of a safety hazard.
HistoryFault Tree Analysis (FTA) attempts to model and analyze failure processes of engineering and biological systems. FTA is basically composed of logic diagrams that display the state of the system and is constructed using graphical design techniques. Originally, engineers were responsible for the development of Fault Tree Analysis, as a deep knowledge of the system under analysis is required. Often, FTA is defined as another part, or technique, of reliability engineering. Although both model the same major aspect, they have arisen from two different perspectives. Reliability engineering was, for the most part, developed by mathematicians, while FTA, as stated above, was developed by engineers. Fault Tree Analysis was initially developed for projects where errors are intolerable (e.g., an error in a nuclear reactor is not tolerated). Bell Telephone Laboratories started the development of FTA during the early 60's for the United States Air Force's Minuteman System (Intercontinental Ballistic Missiles and Bombers). Later, U.S. nuclear power plants and the Boeing Company used the system extensively. FTA can be used as a valuable design tool, can identify potential accidents, and can eliminate costly design changes. It can also be used as a diagnostic tool, predicting the most likely system failure in a system breakdown. FTA is used in safety engineering and in all major fields of engineering. Why Fault Tree Analysis?Since no system is perfect, dealing with a subsystem fault is a necessity, and any working system eventually will have a fault in some place. However, the probability for a complete or partial success is greater than the probability of a complete failure or partial failure. Assembling a FTA is thus not as tedious as assembling a success tree which can turn out to be very time consuming. Because assembling a FTA can be a costly and cumbersome experience, the perfect method is to consider subsystems. In this way dealing with smaller systems can assure less error work probability, less system analysis. Afterward, the subsystems integrate to form the well analyzed big system. MethodologyIn the technique known as "fault tree analysis", an undesired effect is taken as the root ('top event') of a tree of logic. There should be only one Top Event and all concerns must tree down from it. This is also a consequence of another Minuteman Missile System requirement that all analysis be top-down. By fiat there was to be no bottom-up analysis. Then, each situation that could cause that effect is added to the tree as a series of logic expressions. When fault trees are labeled with actual numbers about failure probabilities (which are often in practice unavailable because of the expense of testing), computer programs can calculate failure probabilities from fault trees. The Tree is usually written out using conventional logic gate symbols. The route through a tree between an event and an initiator in the tree is called a Cut Set. The shortest credible way through the tree from fault to initiating event is called a Minimal Cut Set. Some industries use both Fault Trees and Event Trees (see Probabilistic Risk Assessment). An Event Tree starts from an undesired initiator (loss of critical supply, component failure etc) and follows possible further system events through to a series of final consequences. As each new event is considered, a new node on the tree is added with a split of probabilities of taking either branch. The probabilities of a range of 'top events' arising from the initial event can then be seen. Classic programs include the Electric Power Research Institute's (EPRI) CAFTA software, which is used by many of the US nuclear power plants and by a majority of US and international aerospace manufacturers, and the Idaho National Laboratory's SAPHIRE, which is used by the U.S. Government to evaluate the safety and reliability of nuclear reactors, the Space Shuttle, and the International Space Station. Outside the US, the software RiskSpectrum is a popular tool for Fault Tree and Event Tree analysis and is licensed for use at almost half of the worlds nuclear power plants for Probabilistic Safety Assessment. AnalysisMany different approaches can be used to model a FTA, but the most common and popular way can be summarized in a few steps. Remember that a fault tree is used to analyze a single fault event, and that one and only one event can be analyzed during a single fault tree. Even though the ?fault? may vary dramatically, a FTA follows the same procedure for an event, be it a delay of 0.25 msec for the generation of electrical power, or the random launch of an ICBM. FTA analysis involves five steps:
See alsoReferencesExternal links
de:Fehlerbaumanalyse he:?? ???
Source: Wikipedia | The above article is available under the GNU FDL. | Edit this article
|
|
top
©2008-2009 TutorGig.com. All Rights Reserved. Privacy Statement